National Presto Industries, Inc. told the SEC in an Item 1.05 Form 8-K dated March 6, 2025 that a cybersecurity incident caused a system outage on March 1, 2025. The filing describes disruption to shipping, receiving, some manufacturing and back office work, and it does not say that any personal information was involved or give a count of affected people.

Entries like this one, in Wednesday’s docket

Wednesdays

Unsubscribe any time.

What happened and when

The company dates the event to March 1, 2025, the same date it gives as the earliest event reported. It says it responded by bringing in both its own staff and outside specialists.

The filing was signed five days after the outage began. It gives no description of how the incident began or what type of attack it was.

Operational effect and recovery

The company says shipping and receiving, some manufacturing processes and other back-office functions were interrupted, much of it being restored. It also says it put stopgap arrangements in place while systems came back.

The filing does not give a restoration date or say which functions remained down when it was signed.

Financial outlook and notifications

On money, the company stopped short of calling the effect settled. No cost figures, insurance details or revenue estimates appear in the filing.

The company also reports contact with authorities and says more notices may follow.

What Indiana's attorney general recorded

Indiana's attorney general lists National Presto Industries Inc in its 2025 breach report, with notice sent on April 25, 2025 for a breach that occurred on March 1, 2025: 6 Indiana residents and 7,879 people affected in total. The total is the figure the organization reported to Indiana. The breach date is the same March 1 the 8-K gives for the incident.

What Massachusetts recorded

Massachusetts' Office of Consumer Affairs and Business Regulation lists a report from National Presto Industries, Inc. dated April 25, 2025 (breach 2025-733): 7 Massachusetts residents affected. The categories it marks as breached are Social Security numbers and financial account numbers. That count covers Massachusetts residents only.

How National Presto's view of the outage changed

The company's two annual reports since the outage show its assessment moving from open to closed. The 10-K for 2024, filed on March 14, 2025, thirteen days after the outage began, said the full scope was not yet known and that the incident could have a material effect. The same report said the forensic work also covered management's evaluation of internal control over financial reporting.

A year later the answer was in. The 10-K for 2025, filed on March 13, 2026, says the forensic investigation found no material impact on the company's financial condition or results. The 2025 report repeats the list of what the outage interrupted: shipping and receiving, some manufacturing processes and back-office functions, kept going with temporary measures while systems were restored. Neither report gives a cost, an insurance recovery or a restoration date. Neither amends the 8-K.

FilingDateWhat it says about the March 1, 2025 outage
Form 8-K, Item 1.05March 6, 2025Outage reported; disruption to shipping, receiving, manufacturing and back office
Form 10-K, 2024March 14, 2025Scope not yet known; a material impact possible; forensic work continuing
Form 10-K, 2025March 13, 2026Forensic investigation found no material impact

The state records above came in between those two reports. Notices went to Indiana and Massachusetts on April 25, 2025, covering 7,879 people in total by Indiana's count.

What the filing leaves open

The investigation was unfinished when the report was made.

The filing therefore does not say whether data was taken, whether any customer, employee or supplier records were reached, or which business units were affected. It also does not name an attacker or state whether the company expects to file an amendment. The filing does not mention a letter or a notice about personal data. The state records above show that notices went out on April 25, 2025, to 7,879 people in total by Indiana's count.

How this disclosure's timing compares

National Presto Industries disclosed 5 days after the discovery date its filing gives. Across the 46 other filings under 8-K Item 1.05 on cisonews.net that date discovery to the day, the median gap is 6 days.

The rule behind an Item 1.05 filing

Form 8-K Item 1.05 is where a public company reports a cybersecurity incident it has determined to be material. Under the rule the SEC adopted on July 26, 2023, the filing is generally due four business days after the company determines that the incident is material. Source: U.S. Securities and Exchange Commission, press release 2023-139. The guide What is SEC Form 8-K Item 1.05, and what counts as a disclosed cyber incident? reads the rule in full, and the glossary defines Form 8-K Item 1.05.

Other industrials & manufacturing incidents on cisonews.net

All industrials & manufacturing incidents

Sources

  1. 2025-03-06 · ANational Presto Industries, Inc., Form 8-K (SEC EDGAR), published March 6, 2025
  2. 2025-03-14 · ANational Presto Industries, Inc., Form 10-K for 2024 (SEC EDGAR), published March 14, 2025
  3. 2026-03-13 · ANational Presto Industries, Inc., Form 10-K for 2025 (SEC EDGAR), published March 13, 2026
  4. 2026-11-09 · AIndiana Attorney General, 2025 data breach year-to-date report, published November 9, 2026
  5. 2026-11-09 · AMassachusetts Office of Consumer Affairs and Business Regulation, 2025 Data Breach Notification Report, published November 9, 2026
  6. 2023-07-26 · AU.S. Securities and Exchange Commission, press release 2023-139, published July 26, 2023

Tier A: the organization itself (including notices it filed with a state attorney general), a regulator or SEC EDGAR. Tier B: established press. Each fact on this page carries its supporting passage in the page source.

Entries like this one, in Wednesday’s docket

Wednesdays

Unsubscribe any time.